Old Mission
Founded 1804
Capuchin Franciscan
Santa Inés
Solvang, California
Sacred Heart Sisters
Mission Santa Inés

Retrofit

In January, construction work began on the Retrofit Project at Old Mission Santa Inés. To retrofit something means to add a component or accessory that was not there when something was built. For Old Mission Santa Inés, the component missing from the original construction in the early 1800’s was a method to securely join the roof to the adobe walls so that the roof would not collapse during a seismic event or earthquake. Using current engineering and technology, the Retrofit Project addresses this issue to make the roof and walls a strong structural unit that will withstand seismic events.

The Retrofit Project construction work involves bolting 4-foot steel rods that support “L” shaped steel plates in the tops of the original adobe walls at the point where the roof and walls meet as shown on the diagram to the left.

 

 

The workers are working in very tight quarters as shown in this photo to the right.

Once all the "L" shaped steel plates are in place steel beams will be placed on top. The beams will run east to west along the tops of the north and south walls. Several beams will run north to south, connecting the two longer walls together to form a steel cage.

This steel cage will prevent the walls from moving apart or moving towards each other in an earthquake or other seismic event. The roof will remain supported and will not fall into the church.

 

 

During construction, much care is being taken to ensure protection for the walls and floor inside the church. Walls and floors have been covered, and precious artwork has been securely wrapped and safely stored in the Madonna Chapel. The photo on the left shows Fr. Mike Ronayne, our pastor, inspecting some of the stored artwork in the Madonna Chapel. The photo to the right shows Humberto Figueroa, Maintenance and Facilities Director, with a sample 4-foot bolt, L- steel plate, and various lifts used for this project. Note also how the walls and floors are covered as shown in the photo on the right.

Preliminary engineering and fundraising work began on the Retrofit Project over 3 years ago. We have had great support from the community and the parish. Construction work that began in January is expected to be completed sometime this summer. In the interim, Masses continue to be celebrated in our temporary church in the Parish Hall.

We wish to thank everyone who has supported and continues to support this much needed safety work at Old Mission Santa Inés.

Below are some additional photos from this project.


A view of the inside of the church showing how the walls and floor are securely wrapped.

Fr. Mike Ronayne, our pastor, inspecting some of the artwork that is securly wrapped and stored for this project.

Precious artwork securely and safely wrapped and stored in the Madonna Chapel which is not a part of this project.


These are the 4 foot steel rods that will go into the 6 ft thick adobe walls to secure the L-Brackets which hold the beams which tie the walls to the roof structure.


Humberto Figueroa, Maintenance and Facilities Director, inspecting one of the 4 foot steel rods and L-brackets. 

Humberto Figueroa, Maintenance and Facilities Director, showing some of the tools used in this project.


This photo shows how the 4 ft. steel rods fit into the L-brackets.

A close-up of an L-bracked in place. Notice the tight space between the roof and the walls and ceiling floor. Workers also encountered uneven surface on the top of the walls and had to make it level by chipping away excess materials for this project.


Notice how carefully the Santuary has been closed off and protected


Examples of the L-shape brackets


This opening in the ceiling shows how two of the L-brackets are in place


This view of the ceiling opening shows a mock-up of how a beam will be placed.


An example of a beam placement


Walls and floor are well protected

Interior of Church

Lift positioned so work can be done on beam using hole in ceiling.

One of the workers installing beams


Completed steel rod

Corner of roof and ceiling

Completed installation of L brackets


L brackets installed


Beam in place - notice adobe wall to the left

Beams ready to be placed

Protecting the courtyard bricks as well as the mission floor tiles.